This section describes two materialization procedures for Mirror Activator databases in Adaptive Server version 12.5.0.3:
Materializing the standby database (required when the Mirror Activator system is set up)
Re-materializing the primary database for failback
Both of these procedures use the snapshot materialization technique, described in “Materialization options”.
You can use the following procedures to materialize a database in any supported version of Adaptive Server (version 12.5.0.3, or version 12.5.1 or later). However:
If the databases in the Mirror Activator system reside in Adaptive Server version 12.5.0.3, you must use the procedures in this section.
If the databases in the Mirror Activator system reside in Adaptive Server version 12.5.1 or later, you can use either the procedures in this section, or the procedures in “Materializing databases in ASE 12.5.1 or later”.