This section explains how to upgrade the following ETL products to DI Suite 1.2 ETL:
ETL 4.x
Tron 4.x, if none of the following features are used:
UTL projects
XML via SQL Transformer component
XML via XSLT Transformer component
Job Guard Calculation
Job project pre-processing or post-processing
Global variables
ETL Small Business Enterprise (SBE)
IQEEE
The upgrade procedure for ETL Server and ETL Development is the same for all the ETL products listed above. The only exception is that you need to obtain the new DI 1.2 Sybase ETL Server and DI 1.2 Sybase ETL Development licenses while upgrading all ETL products, except ETL 4.x.
Upgrading Sybase ETL
Server
At the command prompt, shut down any running GridNode:
./GridNode.sh --shutdown
Verify that the GridNode has shut down successfully:
ps -e | grep GridNode
If the GridNode is still running, kill the process.
Use the DI Suite installer to install the new version of Sybase ETL Server in the same installation directory as the existing one.
If you are upgrading from Tron 4.x, ETL SBE and IQEEE, obtain the new DI Suite 1.2 Sybase ETL Server licenses from the SPDC and copy it into the $SYBASE/ETLServer42/licenses directory.
See the Sybase Software Asset Management User's Guide.
If you are upgrading from ETL 4.x, do not perform this
task.
Start the new ETL Server.
To start the ETL Server directly, enter:
GridNode.sh
To start the ETL Server as a service, enter:
GridNode --install
To verify whether the startup is successful, enter:
ps -e | grep GridNode